Piping Lead Engineer has to perform various activities to ensure smooth execution of piping engineering work with appropriate quality control. Some of such activities are Field Trips, Preliminary Job Site Survey, Fabrication Inspection Trips, Support Activities, Front End Planning etc. Typical manhours required for each of these activities are as follows.

Sr.Activity / UnitHours
1Preliminary Job Site Survey : Field Trips / Per Day8
2Construction Work Package Preparation / Per Package20
3Construction Support Trips / Per Week40
4Fabrication Shops Survey / Per Day8
5Department Management Review / Per Meeting2
6Technical Support Activities / Per Day2
7Technical Assistants (Area Engineers etc.) / Per Week80
8Front End Planning : One Time120
9Supervision Activities : 10% of Total Above10%